A sign without a permit in Ontario can lead to a notice or order to comply, a fine, and removal of the sign at the owner’s cost. A ticket has a maximum fine of $1,000, but a court conviction under a sign by-law can bring a fine of up to $100,000. The fastest fix is to apply for a permit for the sign, or to remove it, before the date on the notice.

Two laws can apply to one sign

A sign by-law is the municipal law that sets the size, location and type of signs, and when a sign needs a sign permit. Each municipality has its own. For example, section 4(1) of the Mississauga Sign By-law 0054-2002 says no person can erect, display or alter a sign in the City without a permit, except the signs the by-law exempts.

The Building Code Act, 1992 is the provincial law for construction. Section 8(1) of the Building Code Act says no person can construct a building without a permit from the chief building official. The Act’s definition of “building” includes structures that the Building Code designates. In Toronto, the City’s sign inquiries page says a sign on a building or in the ground needs a sign permit and a building permit.

To find out which permits your sign needs, see Do I need a sign permit in Ontario? or order a Sign Code Check.

Sign without permit consequences: fines and costs

The table shows the maximum amounts in the laws. A fine in a given case can be lower.

Consequence Law and section Amount or effect
Ticket (offence notice) Provincial Offences Act, s.12(1) Not more than $1,000
Toronto fine for a sign with no permit City of Toronto $305
By-law fine on conviction Municipal Act, 2001, s.429(3) Up to $100,000. Daily fines up to $10,000, with no total limit
Toronto fine on conviction Chapter 694, 694-27A and D $500 to $100,000. First party sign: $250 to $10,000 for each day
Mississauga fine on conviction By-law 0054-2002, s.31(1.1) $500 to $100,000
Building Code Act fine, person Building Code Act, s.36(3) Up to $50,000 (first offence), $100,000 (later offence)
Building Code Act fine, corporation Building Code Act, s.36(4) Up to $500,000 (first offence), $1,500,000 (later offence)
Removal by the municipality Municipal Act, 2001, s.446 Cost added to the tax roll, with interest up to 15%
Mississauga removal and storage By-law 0054-2002, s.31(6) and (7) $200 for each sign or the City’s cost, whichever is greater. Storage $20 a day or $2/m² of sign face a day, whichever is greater
Toronto permit after a violation Sign-related fees Administrative fee of $963.71 for each sign face

Ticket or court summons

Municipalities enforce by-laws under the Provincial Offences Act. A ticket is a charge under Part I of that Act. Section 12(1) limits the fine on a ticket to $1,000. A charge under Part III is a summons to court. In that case, the higher fines in the by-law and in section 429 of the Municipal Act, 2001 apply. A continuing offence is an offence that occurs again each day the sign stays up. The Municipal Act lets a municipality set a fine for each day.

Orders you can receive

An order to comply is a written order that tells you what is wrong and the date to fix it. The name of the notice changes from city to city.

  • Toronto Notice of Violation: under Chapter 694, the Toronto Sign By-law, the Chief Building Official can give you 14 days to make the sign comply (694-28A). After 14 days, the City can remove the sign or cover its copy (694-28B). See our guide to the sign Notice of Violation in Toronto.
  • Mississauga notice: the City can order you to remove, repair or replace the sign, or make it comply, by a set date (s.31(2)(b)). If the sign is a safety hazard or is on public property, the City can remove it at once with no notice (s.31(2)(a)).
  • Municipal Act orders: a municipality can order you to stop the activity (s.444) or to do work to correct it (s.445). If you do not comply, the municipality can do the work at your expense (s.446).
  • Building Code Act orders: an inspector can make an order to comply (s.12(2)). If you do not comply, the chief building official can make a stop work order (s.14). A person who does not comply with a stop work order can be fined up to $10,000 for each day (s.36(6)).

An order can stay with the property

An order under section 12 of the Building Code Act can be posted on the site, posted on the municipality’s website, or registered on title (s.12(5)). A person who buys an interest in the land after the registration is deemed to have been served with the order (s.12(6)). The order stays on title until the chief building official registers a certificate that the work is done (s.12(7)). This matters when you sell the business or the property.

Who is responsible: tenant, landlord or sign company?

More than one person can be responsible for the same sign:

  • The person who put up the sign, or caused it: Toronto’s by-law applies to any person who erected, displayed, modified or restored a sign without a permit, or caused it (694-28A). This can include the tenant and the sign company.
  • The owner or occupier of the land: Municipal Act orders under sections 444 and 445 can go to the person who contravened the by-law, the person who caused or permitted it, or the owner or occupier of the land.
  • The property owner pays for removal: removal costs can go on the tax roll for the property (Municipal Act, s.446(3); Toronto 694-28B).
  • Directors and officers: a director or officer of a corporation who knowingly concurs in the offence is also guilty of an offence (Building Code Act, s.36(2); Toronto 694-27C(13)).

Before you install a sign, agree in writing with your landlord and your sign company who applies for the permit.

What to do if your sign has no permit

  1. Read the notice. Find the compliance date, the sign it refers to, and the inspector’s name.
  2. Call the inspector before the date. Tell the inspector your plan and your date to apply.
  3. Check the sign against the sign by-law. A Sign Code Check tells you if the sign needs a permit only, or a variance first.
  4. Get drawings of the existing sign. The City needs a site plan, elevations and sign details. We prepare sign permit drawings from site measurements and photos.
  5. Apply for the permit. Pay any administrative fee for a sign put up before the permit.
  6. Apply for a variance if the sign does not comply. A variance is a formal approval of a sign that does not meet one or more by-law rules. See our sign variance service.
  7. Send the application number to the inspector. This shows that you act to comply.
  8. Remove the sign if you cannot get a permit. Remove it before the compliance date.

If you have a sign with no permit and no notice yet, follow steps 3 to 7. See Already have a sign but no permit?

Need help with a sign that has no permit?

Send us the address, photos of the sign, the notice (if you have one), the landlord’s contact and your compliance date. We reply within one business day with the permit or variance path for your sign. See our sign permit service, our services for property managers, or contact us.

This article is general information, not legal advice. For an order or a court summons, speak to a lawyer or a licensed paralegal.

Need help with your sign permit?

Tell us about your project and we'll reply within one business day with next steps and a quote.

See our sign permit services.