Applicable Law Approvals for Sign and Building Permits
The City cannot issue your sign permit or building permit until other agencies approve the work. We get these approvals for you.
- Ministry of TransportationMTOSign permit and encroachment permit for work near provincial highways.MTO approvals ↓
- Transit corridorsMetrolinxExemption or Corridor Development Permit for work near transit corridor land.Metrolinx approvals ↓
- TRCA, CVC, Conservation Halton, HCA and moreConservation Authority ClearancePermit or clearance letter for work near rivers, valleys, wetlands and shorelines.Conservation authority clearance ↓
Why the City asks for these approvals
Section 8(2)(a) of the Building Code Act says that the chief building official must not issue a permit if the work does not comply with "applicable law".
The Ontario Building Code lists applicable law in Division A, Article 1.4.1.3. The list includes:
- Conservation Authorities Act, sections 28 to 28.1.2. Development in a regulated area near rivers, valleys, wetlands and shorelines.
- Public Transportation and Highway Improvement Act, sections 34 and 38. Buildings, structures and signs near provincial highways.
- Building Transit Faster Act, 2020, section 3. Buildings and structures on or near transit corridor land.
Signs are included. A ground sign or pylon sign is a designated structure under Division A, Article 1.3.3.5, so it needs a building permit. A sign on a building is an alteration to that building. If the property is in an MTO, Metrolinx or conservation authority area, the examiner puts the application on hold until you supply the approval.
Many sign projects stop at this step because nobody checked the property before the application. We check it before we submit, and we get the approval in parallel with the permit drawings.
Conservation Authority Clearance
Ontario conservation authorities control development on land near rivers, streams, valleys, wetlands and the shorelines of the Great Lakes and inland lakes.
Under section 28 of the Conservation Authorities Act and Ontario Regulation 41/24, you need a permit from the conservation authority for development in a regulated area. The regulation came into force on April 1, 2024. It applies the same rules to all conservation authorities.
Why clearance is needed
- Flood and erosion hazards. The authority checks that the work does not affect the control of flooding, erosion, dynamic beaches or unstable soil or bedrock.
- Safety of people and property. The authority checks that the work does not put people or property at risk during a flood or a slope failure.
- A sign is a structure. "Development activity" includes the construction or placing of a building or structure of any kind. A pylon sign foundation in a flood plain is development.
- The regulated area is wide. It includes flood plains, valleys plus 15 metres from the top of the bank, and land within 30 metres of a wetland. Many commercial plazas are in these areas.
- The City cannot skip it. The examiner sees the regulated area on the City map. The permit stays on hold until the authority approves the work.
- Fines and orders. Work in a regulated area without approval breaks the Act. The authority can order you to remove the work.
Permit or clearance letter
Each conservation authority has its own forms, fees and review times. If the work needs a permit, the authority issues a permit. If the work does not need a permit, many authorities issue a clearance letter or a written response that says so. For example, Cataraqui Conservation and Essex Region issue clearance letters, and the Grand River Conservation Authority issues a title clearance letter. TRCA says that "a TRCA permit is required prior to obtaining a building permit from your municipality" when the work is in its regulated area.
A wall sign on an existing building usually gets a fast clearance. A new ground sign, pylon sign or foundation near a watercourse usually needs a full permit with a site plan and drawings.
What we do
- Check the property on the regulated area map of the conservation authority.
- Ask for pre-consultation when the authority requires it.
- Prepare the application, the site plan and the sign drawings.
- Pay the authority fee on your behalf and answer its comments.
- Send the permit or clearance letter to the City examiner.
Ontario conservation authorities
Central Lake Ontario Regional Conservation Authority
From February 1, 2027. Includes:
Toronto and Region Conservation Authority (TRCA)
Toronto, Vaughan, Markham, Richmond Hill, Pickering, Ajax
Central Lake Ontario Conservation Authority (CLOCA)
Oshawa, Whitby, Clarington, Scugog
Western Lake Ontario Regional Conservation Authority
From February 1, 2027. Includes:
Credit Valley Conservation (CVC)
Mississauga, Brampton, Caledon, Halton Hills, Orangeville
Conservation Halton
Burlington, Oakville, Milton, Halton Hills, Flamborough
Hamilton Conservation Authority (HCA)
Hamilton, Ancaster, Dundas, Stoney Creek, Glanbrook
Niagara Peninsula Conservation Authority (NPCA)
St. Catharines, Niagara Falls, Welland, Grimsby
Eastern Lake Erie Regional Conservation Authority
From February 1, 2027. Includes:
Grand River Conservation Authority (GRCA)
Kitchener, Waterloo, Cambridge, Guelph, Brantford
Long Point Region Conservation Authority (LPRCA)
Norfolk County, Tillsonburg, Haldimand
Kettle Creek Conservation Authority (KCCA)
St. Thomas, Central Elgin, south London
Catfish Creek Conservation Authority (CCCA)
Aylmer, Central Elgin, Malahide
Western Lake Erie Regional Conservation Authority
From February 1, 2027. Includes:
Upper Thames River Conservation Authority (UTRCA)
London, Woodstock, Stratford, St. Marys, Ingersoll
Essex Region Conservation Authority (ERCA)
Windsor, LaSalle, Tecumseh, Leamington, Amherstburg
Lower Thames Valley Conservation Authority (LTVCA)
Chatham-Kent, West Elgin, Southwest Middlesex
St. Clair Region Conservation Authority (SCRCA)
Sarnia, Petrolia, Strathroy-Caradoc
Lake Huron Regional Conservation Authority
From February 1, 2027. Includes:
Lake Simcoe Region Conservation Authority (LSRCA)
Newmarket, Aurora, Georgina, Innisfil, East Gwillimbury
Nottawasaga Valley Conservation Authority (NVCA)
Barrie, Collingwood, Wasaga Beach, New Tecumseth
Grey Sauble Conservation Authority (GSCA)
Owen Sound, Meaford, Georgian Bluffs
Saugeen Valley Conservation Authority (SVCA)
Hanover, Walkerton, Kincardine, Saugeen Shores
Maitland Valley Conservation Authority (MVCA)
Goderich, Wingham, Huron East, North Perth
Ausable Bayfield Conservation Authority (ABCA)
Grand Bend, Bluewater, South Huron, Central Huron
Eastern Lake Ontario Regional Conservation Authority
From February 1, 2027. Includes:
Ganaraska Region Conservation Authority
Port Hope, Cobourg, east Clarington
Kawartha Conservation
Kawartha Lakes, Scugog, Brock
Otonabee Conservation
Peterborough, Selwyn, Douro-Dummer
Lower Trent Conservation
Quinte West, Brighton, Trent Hills
Crowe Valley Conservation Authority
Marmora and Lake, Havelock-Belmont-Methuen
Quinte Conservation
Belleville, Prince Edward County, Greater Napanee
Cataraqui Conservation
Kingston, Loyalist, South Frontenac
St. Lawrence River Regional Conservation Authority
From February 1, 2027. Includes:
Rideau Valley Conservation Authority (RVCA)
Ottawa, Smiths Falls, Perth, North Grenville
Mississippi Valley Conservation Authority
west Ottawa, Carleton Place, Mississippi Mills
South Nation Conservation (SNC)
east Ottawa, Russell, Clarence-Rockland
Raisin Region Conservation Authority (RRCA)
Cornwall, South Glengarry, South Stormont
Northeastern Ontario Regional Conservation Authority
From February 1, 2027. Includes:
Conservation Sudbury (Nickel District)
Greater Sudbury
North Bay-Mattawa Conservation Authority
North Bay, Callander, East Ferris, Mattawa
Sault Ste. Marie Region Conservation Authority
Sault Ste. Marie, Prince Township
Mattagami Region Conservation Authority
Timmins
Northwestern Ontario Regional Conservation Authority
From February 1, 2027. Includes:
Lakehead Region Conservation Authority
Thunder Bay, Neebing, Shuniah, Oliver Paipoonge
MTO Approvals
The Ministry of Transportation (MTO) controls land next to provincial highways under the Public Transportation and Highway Improvement Act.
- MTO sign permit. You need one for a sign within 400 metres of the limit of a provincial highway. This includes the 400-series highways. A business sign, a pylon sign and a billboard all need it.
- MTO encroachment permit. You need one for any work on, under or in the highway right-of-way, for example a sign, a banner or a utility connection.
- MTO building and land use permit. You need one for a building or structure within 45 metres of the highway limit, or near an intersection. A new sign structure can need this permit too.
MTO takes applications through its Highway Corridor Management System. You can check if a property is in the MTO permit control area. MTO sets the sign rules and setbacks in Chapter 5 of its Highway Corridor Management Manual. Fees are on the highway corridor management page.
We prepare the MTO application, the site plan with the setback to the highway limit, and the sign drawings. We answer the comments of the MTO corridor management office and send the MTO permit to the City examiner.
Metrolinx Approvals
Metrolinx controls work on and near transit corridor land under section 3 of the Building Transit Faster Act, 2020.
You need a Corridor Development Permit (CDP) to build, alter or place a building or other structure on transit corridor land or within 30 metres of it. Work on utilities within 10 metres also needs a permit. The rule started with the Ontario Line, the Yonge North Subway Extension, the Scarborough Subway Extension and the Eglinton Crosstown West Extension. Since 2025, it can apply to other provincial transit projects.
Metrolinx says that "even small scale or minor projects require a permit". Its guideline also says that the municipality issues its permit only when the Corridor Development Permit is in hand. Some project types are exempt. Metrolinx confirms each exemption case.
- Exemption. For work that is on the Metrolinx exempt list. We send the project details to Metrolinx and get written confirmation for the City.
- Corridor Development Permit. For new signs, sign structures and other work that is not exempt. We prepare the pre-application form, the application form, the site plan and the drawings.
Check the property on the Metrolinx third-party coordination and permitting map. Details are on the Metrolinx Corridor Development Permit page. Near GO rail corridors, Metrolinx also reviews development under its GO adjacent development guidelines.
How we get your approvals
Property check
We check the address against the MTO, Metrolinx and conservation authority maps and the municipal applicable law checklist.
Agency contact
We confirm with each agency if the work needs a permit, an exemption or a clearance letter.
Application package
We prepare the forms, the site plan, the sign drawings and the owner authorization, and we submit them.
Review and comments
We answer the agency comments and follow up until the agency issues the approval.
Approval to the City
We send the approval to the City examiner so that the sign permit or building permit can be issued.
Frequently asked questions
What is an applicable law approval?▾
It is an approval from another agency that the Building Code lists as "applicable law". The chief building official cannot issue a building permit until the work complies with applicable law. Approvals from conservation authorities, the Ministry of Transportation (MTO) and Metrolinx are on this list.
Does a sign permit need applicable law approvals?▾
Often, yes. Ground signs and pylon signs are designated structures under the Ontario Building Code, so they need a building permit. A sign on a building is an alteration to the building. The City checks applicable law for both before it issues the permit.
What is conservation authority clearance?▾
It is the written approval from the conservation authority that the City needs before it issues your permit. If the work needs a permit under section 28 of the Conservation Authorities Act, the authority issues a permit. If the work does not need a permit, many authorities issue a clearance letter or a written response. The City accepts either one.
How do I know if my property is in a conservation authority regulated area?▾
Use the regulated area map of the conservation authority for your area. The links are in the list on this page. If the map is not clear, the authority can confirm in writing for a fee. We can do this check for you.
Do I need an MTO sign permit?▾
You need an MTO sign permit if the sign is within 400 metres of the limit of a provincial highway. The rule is in sections 34 and 38 of the Public Transportation and Highway Improvement Act. Work inside the highway right-of-way needs an MTO encroachment permit.
What is a Metrolinx Corridor Development Permit?▾
It is a permit under section 3 of the Building Transit Faster Act, 2020. You need one to build, alter or place a building or other structure on transit corridor land or within 30 metres of it. A sign is a structure. The City issues its permit only after you have the Corridor Development Permit or confirmation from Metrolinx that your project is exempt.
Can a sign project be exempt from a Metrolinx permit?▾
Some projects are exempt, for example some interior work and some façade work. Metrolinx publishes a list of exempt project types and confirms each case. We send the project details to Metrolinx and get the confirmation for the City.
What happens to conservation authorities in 2027?▾
On February 1, 2027, Ontario combines its 36 conservation authorities into 9 regional conservation authorities. Applications that are in progress on that date continue with the new regional authority. We track the change and use the correct authority for each application.
Related services