How to Get a Sign Permit in Surrey, BC

You need a sign permit in Surrey, BC, for any new sign and to reface an existing sign, unless the Surrey Sign By-law No. 13656 exempts it. You apply online through the City’s permitting portal or by email. The permit fee starts at $216 for a sign of up to 3 m² (32 sq. ft.), plus a $100 processing fee that the City credits to the permit fee.
Do you need a sign permit in Surrey?
Section 12(1) of the Surrey Sign By-law No. 13656 (consolidated to June 29, 2026) requires a sign permit before you erect a new sign or change an existing sign, including a relocation. The City’s sign permit page adds that a refaced sign also needs a permit.
Section 7 exempts some signs from the permit and the inspection. Examples are up to three small window signs for each premises (7(12)), on-site directional signs of up to 0.4 m² (7(16)) and interior signs that are not visible from outside (7(20)). Exempt signs must still comply with the by-law.
Section 10 prohibits roof signs, billboards, inflatable signs, electronic message board signs and window signs above the first storey. Section 10(15) also prohibits a sign that shows a phone number, website or email address.
Key sign rules in commercial and industrial zones
- Fascia signs (27(2)): two for each premises, not on the same façade. Large premises of 3,000 m² or more can have up to six. The sign projects 0.5 m or less.
- Total sign area (6(14)): the combined area of the fascia, awning, canopy, projecting and window signs on a lot cannot exceed 1 m² for each linear metre of premises frontage.
- Free-standing signs (27(1)): one for each lot line next to a highway, except a lane, with a minimum 2 m setback. The limits are 14 m² for a single-faced sign and 4.5 m height, or 6 m along the roads listed in 27(1)(h).
A sign code check finds these problems before you apply.
Sign permit requirements in Surrey: drawings and documents
Every application needs the Sign Permit Application Checklist (updated July 2026). The City rejects an application that does not include all required documents. Prepare:
- The Sign Permit Application Form, with the sign description, all contacts and the construction value.
- A site plan with the building, the street names, a north arrow, the signs to scale and the dimensioned premises frontage.
- An elevation for each wall with a sign, with the dimensions of the sign and of the lettering.
- Sign drawings and a cross section with the illumination, the materials and the wall anchorage detail.
- For a free-standing sign: the foundation details, the property lines, the height from grade and the development permit number.
- An Owner Authorization Form if the owner does not sign, and a business licence or the City’s reply to a Bylaw & Licensing Inquiry Form.
Our sign permit drawings service prepares plans to this checklist.
When you need an engineer
The City requires structural drawings signed and sealed by a Registered Professional for fascia signs over 68 kg (150 lb), free-standing signs over 2.5 m (8 ft. 2 in.) high, awning and canopy signs, and complex signs. Give a Schedule B and a certificate of insurance before the City issues the permit. Under Section 14(1), a BC professional engineer must also inspect the construction of an engineered sign, and the owner submits the engineer’s certificate. See our sign engineering service.
How to apply for a sign permit in Surrey
- Check the zoning and any development permit (DP) or development variance permit (DVP) on the site.
- Get any permits that must come first, such as a building permit for a new awning, canopy or tenant space, or a DP for a new free-standing sign.
- Prepare the drawings, the forms and the checklist.
- Submit through the permitting portal with a MySurrey account. The permitting portal guide explains how to get an access code.
- Or submit by email to permitapplication@surrey.ca. The digital submission guide requires a separate PDF for each document.
- Pay the $100 processing fee and reply to each deficiency comment.
- Install the sign and book the final inspection.
If the sign does not comply
Section 9 allows variances through a DVP. Under Bylaw No. 20620, a City official can issue a minor DVP for signage. The City’s delegated DVP page says that minor signage variances need no public notice. The DVP fee is $750 for a minor variance and $1,500 for a general variance (Bylaw 18641, s. 17). Read more about sign variances and what a sign variance is.
Surrey sign permit fees (2026)
The permit fee uses the total area of all sign faces (Section 13(1)(b)). Taxes are extra. Sign fees are in Schedule L of the Fee-Setting By-law No. 14577 (consolidated to June 29, 2026). DP and DVP fees are in the Development Application Fees Bylaw No. 18641 (consolidated to July 27, 2026).
| Item | Fee | Source |
|---|---|---|
| Processing fee (credited to the permit fee) | $100 | Schedule L |
| Sign up to 3 m² (32 sq. ft.) | $216 | Schedule L |
| Over 3 m² up to 6 m² (64 sq. ft.) | $318 | Schedule L |
| Over 6 m² up to 10 m² (110 sq. ft.) | $423 | Schedule L |
| Over 10 m² up to 15 m² (160 sq. ft.) | $532 | Schedule L |
| Over 15 m² up to 18.6 m² (200 sq. ft.) | $612 | Schedule L |
| Over 18.6 m² (200 sq. ft.) | $818 | Schedule L |
| Relocation or alteration on the same lot | $192 | Schedule L |
| Electrical permit, if applicable | $177 | City fee page |
| Delegated DP: new free-standing signs | $823 | Bylaw 18641, s. 20.1 |
| DVP: minor variance | $750 | Bylaw 18641, s. 17 |
Other approvals you may need
- Development permit: required for a new free-standing sign. A DP can also limit the type, design and location of signs on a site.
- Electrical permit: a sign with an electrical connection must comply with the Surrey Electrical Safety By-law (Section 14(3)). The City typically processes electrical permits within seven business days.
- Provincial highways: a sign in a provincial highway right-of-way must meet the provincial ministry’s requirements (Section 5(3)). Section 6(5) bans most signs within 150 m of Highways No. 1 and No. 99.
- Insurance: a sign over a highway, sidewalk or public place needs a liability policy of at least $5,000,000 that names the City (Section 13(2)).
Sign permit timeline and inspections in Surrey
The City does not publish a processing time for sign permits. The application form states that an application becomes void after six months unless the City grants an extension in writing. Schedule L also lets the City cancel an application and keep the fees if it cannot issue the permit within 180 days after it tells you about deficiencies.
A final inspection is required after you install the sign and finish the electrical work. Book it in the permitting portal. The City’s building inspections page states that from January 1, 2027, you cannot book inspections by phone. Under Section 16, each offence carries a penalty of $100 to $2,000.
For other western cities, read our Calgary, Edmonton and Winnipeg sign permit guides. Brands with many locations can use our national franchise permit program.
Need help with your Surrey sign permit?
Rouge Hill Consulting prepares sign permit drawings, engineering and applications for businesses and sign companies across Canada. Send your address, sign artwork and site photos through our contact page. We reply within one business day. See our sign permit services for what we include.